Why must risk attitude be considered as a part of risk analysis?
Todd is the project manager of the EST project for his company. His organization has established
certain rules in the enterprise environmental factors which affect the approach that Todd takes in
managing his project. One of the rules requires Todd to consider the risk attitude of the
stakeholders participating in risk analysis. Why must risk attitude be considered as a part of risk
analysis?
what is likely to increase?
[tagged]
You work as the project manager for Bluewell Inc. There has been a delay in your project work
that is adversely affecting the project schedule. You decide, with your stakeholders’ approval, to
fast track the project work to get the project done faster. When you fast track the project, what is
likely to increase?