What type of analysis is Mary using in this project?

[tagged]
Mary is the project manager of PKT project. In Mary’s project there are certain enterprise
environmental factors that require Mary to use modeling and simulation techniques to predict the
likelihood of achieving cost and schedule objectives in the project. Mary is using a technique for
which the cost estimates are chosen at random for each iteration of the analysis, such as
pessimistic, most likely, and worst-case scenarios. What type of analysis is Mary using in this
project?

What is the primary advantage to group risks by common causes during qualitative risk analysis?

Courtney is the project manager for her organization. She is working with the project team to
complete the qualitative risk analysis for her project. During the analysis Courtney encourages the
project team to begin the grouping of identified risks by common causes. What is the primary
advantage to group risks by common causes during qualitative risk analysis?

What should Lamont do with the risk responses he identified during the project’s monitoring and controll

Lamont is the project manager of a project that has recently finished the final project deliverables.
The project customer has signed off on the project deliverable and Lamont has a few
administrative closure activities to complete. In the project, there were several large risks that
could have wrecked the project but Lamont and his project team found some creative methods to
resolve the risks without affecting the project costs or project end date. What should Lamont do
with the risk responses he identified during the project’s monitoring and controlling process?

Which output of the manage stakeholder expectations process can create risks?

[tagged]
Harold is the project manager of a large project in his organization. He has been actively
communicating and working with the project stakeholders. One of the outputs of the manage
stakeholder expectations process can actually create new risk events for Harold’s project. Which
output of the manage stakeholder expectations process can create risks?

What risk response has management asked Harry to implement?

Harry is the project manager of the MMQ Construction Project. In this project, Harry has identified
a supplier who can create stained glass windows for 1,000 window units in the construction
project. The supplier is an artist who works by himself, but creates windows for several companies
throughout the United States. Management reviews the proposal to use this supplier and while
they agree that the supplier is talented, they do not think the artist can fulfill the 1,000 window units
in time for the project’s deadline. Management asked Harry to find a supplier who can fulfill the
completion of the windows by the needed date in the schedule. What risk response has
management asked Harry to implement?

What key thing will help Joan to discover risks within the review of the project documents?

Joan is a project management consultant and she has been hired by a firm to help them identify
risk events within the project. Joan would first like to examine the project documents including the
plans, assumptions lists, project files, and contracts. What key thing will help Joan to discover
risks within the review of the project documents?

What risk response is the most appropriate for this instance?

Rob is the project manager of the IDLK Project for his company. This project has a budget of
$5,600,000 and is expected to last 18 months. Rob has learned that a new law may affect how the
project is allowed to proceed – even though the organization has already invested over $750,000
in the project. What risk response is the most appropriate for this instance?