What project management process would best help you?
[tagged]
You are the project manager of the NHQ Project for your company. You have completed
qualitative and quantitative analysis of your identified project risks and you would now like to find
an approach to increase project opportunities and to reduce threats within the project. What
project management process would best help you?
what specific goal in mind?
Virginia is the project manager for her organization. She has hired a subject matter expert to
interview the project stakeholders on certain identified risks within the project. The subject matter
expert will assess the risk event with what specific goal in mind?
Which one of the following is NOT a probable reason for relying on organizational process assets as an input f
You are preparing to start the qualitative risk analysis process for your project. You will be relying
on some organizational process assets to influence the process. Which one of the following is
NOT a probable reason for relying on organizational process assets as an input for qualitative risk
analysis?
Which of the following diagrams will you create to accomplish the task?
[tagged]
You work as a project manager for BlueWell Inc. You want to create a visual diagram, which can
depict the resources that will be used within the project. Which of the following diagrams will you
create to accomplish the task?
What will be the expected monetary value of Risk C?
Which project management plan will be the best guide for John to communicate to the external stakeholders?
[tagged]
John is the project manager of the NHQ Project for his company. His project has 75 stakeholders,
some of which are external to the organization. John needs to make certain that he communicates
about risk in the most appropriate method for the external stakeholders. Which project
management plan will be the best guide for John to communicate to the external stakeholders?
what is the risk exposure of the event that must be considered for the cost of the risk response?
You are the project manager of the KJH Project and are working with your project team to plan the
risk responses. Consider that your project has a budget of $500,000 and is expected to last six
months. Within the KJH Project you have identified a risk event that has a probability of .70 and
has a cost impact of $350,000. When it comes to creating a risk response for this event what is the
risk exposure of the event that must be considered for the cost of the risk response?
What risk identification technique allows participants to identify the project risks and to remain anonymous?
[tagged]
What risk identification technique allows participants to identify the project risks and to remain
anonymous?
which of the following processes is John working on?
[tagged]
John works as a project manager for ABD project. He and his team, are working on the following
activities:
Relative ranking or priority list of project risks
Watchlists of low priority risk
Trends in Qualitative Risk Analysis results
On which of the following processes is John working on?
Which one of the following is NOT an output of the process?
[tagged]
There are five outputs of the risk monitoring and controlling process. Which one of the following is
NOT an output of the process?