Which of the following is an input to Develop Human Resource Plan?
Which of the following is an input to Develop Human Resource Plan?
Which of the following is an input to the Qualitative Risk Analysis process?
Which of the following is an input to the Qualitative Risk Analysis process?
At the end of the project, what will be the value of SV?
At the end of the project, what will be the value of SV?
Which is one of the determining factors used to calculate CPI?
Which is one of the determining factors used to calculate CPI?
Based on the following metrics: EV=$20,000, AC=$22,000 and PV=$28,000, what is the project CV?
Based on the following metrics: EV=$20,000, AC=$22,000 and PV=$28,000, what is the project CV?
What does a CPI value greater than 1.0 indicate?
What does a CPI value greater than 1.0 indicate?
Which type of tool would be used for the quality planning activity?
Which type of tool would be used for the quality planning activity?
Analogous Cost Estimating relies on which of the following techniques?
Analogous Cost Estimating relies on which of the following techniques?
What is the cost performance index?
The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected:
Actual cost = $50,000
Plan cost = $45,000
Earned value = $40,000
What is the cost performance index?
What is CPI?
The PV is $1000, EV is $2000 and AC is $1500. What is CPI?