which type of performing is present in this scenario?
A program has a BAC of $1,750,000 and is expected to last two years. The program is currently at the third milestone which represents 35 percent of the program work. As it happens, this program has already spent $620,000 of the budget. Management is concerned that the program may also be slipping on schedule because the program should be forty percent complete by this time.
Based on this information which type of performing is present in this scenario?
Which one of the following is a likely reason why the project should be terminated?
Mary Anne is the program manager for her organization. In her program there are six projects.
One of the projects in her program has been performing well. It is on schedule and has no cost or schedule variances. Mary Anne has decided, however, that her program needs to be terminated.
Which one of the following is a likely reason why the project should be terminated?