Scope, schedule, and cost parameters are integrated in the: seenagape 10 years ago Scope, schedule, and cost parameters are integrated in the: A.Performance measurement baseline. B.Analysis of project forecasts, C.Summary of changes approved in a period, D.Analysis of past performance. ← Previous question Next question →