which risk response?

The risk management team of a software project has decided that due to the lack of adequate
talent in the company, development of a specific part of the system is under high risk, so the team
has decided to outsource it. This is an example of which risk response?

A.
Transfer

B.
Share

C.
Avoid

D.
Accept