PMI Exam Questions

Resource reallocation from non critical to critical activities is an example of which Project Schedu

Resource reallocation from non critical to critical activities is an example of which Project Scheduling technique:

A.
Critical Path Method

B.
Schedule Compression

C.
Resource Leveling

D.
What if Analysis

Explanation:
Resource Leveling: Allocate scare resources to critical path activities first.