Parametric Estimating is done as a part of which process:

Parametric Estimating is done as a part of which process:

A.
Estimate Activity Durations

B.
Sequence Activities

C.
Develop Schedule

D.
Estimate Activity Resources

Explanation:
Tools and Techniques for Estimate Activity Durations are: Analogous estimates , Parametric Estimating, Three-Point Estimates and Reserve Analysis.