PMI Exam Questions

Lessons learned can be used to:

Lessons learned are most often based upon project historical records. Lessons learned can be used to:

A.
See how others have solved problems

B.
“Predict trends, highlight problems and identify alternatives”

C.
See what mistakes others have made

D.
All of the other alternatives apply