Overlapping activities on a project, such as design and construction, is referred to as: admin 11 years ago Overlapping activities on a project, such as design and construction, is referred to as: A.Process improvement. B.Synchronous manufacturing C.Fast tracking D.Parallel management. E.Risk conversion. ← Previous question Next question →