If the PMO receives the following information, which project should they be the MOST concerned about

The project management office is worried about the quality of the company’s various projects. They want to know which projects are having problems and which ones are doing well. If the PMO receives the following information, which project should they be the MOST concerned about?

A.
Project A with a benefit cost ratio of 2.3

B.
Project B with a benefit cost ratio of 1.3

C.
Project C with a benefit cost ratio of negative 2.3

D.
Project D with a benefit cost ratio of negative 1.3