During the initial stages of the project, what do activity attributes include?

During the initial stages of the project, what do activity attributes include?

A.
Activity name, dependencies, assumptions

B.
Activity ID, WBS ID, activity name

C.
Activity ID, assumptions, constraints

D.
Activity name, WBS ID, activity description