Who provides the inputs for the original estimates of activity durations for tasks on the project plan?
Who provides the inputs for the original estimates of activity durations for tasks on
the project plan?
which process?
Control charts, flowcharting, histograms, Pareto charts, and scatter diagrams are
tools and techniques of which process?
what is the expected duration of the activity?
A given schedule activity is most likely to last four weeks. In a best-case scenario,
the schedule activity is estimated to last two weeks. In a worst-case scenario, the
schedule activity is estimated to last 12 weeks. Given these three estimates, what is
the expected duration of the activity?
What is the primary benefit of meeting quality requirements?
What is the primary benefit of meeting quality requirements?
Which of the following outputs from the Control Schedule process aids in the communication…?
Which of the following outputs from the Control Schedule process aids in the
communication of schedule variance (SV), schedule performance index (SPI), or any
performance status to stakeholders?
which of the following categories of cost of quality?
Testing falls into which of the following categories of cost of quality?
Which of the following events would result in a baseline update?
Which of the following events would result in a baseline update?
Which of the following schedule network analysis techniques is applied when a critical path method calculation
Which of the following schedule network analysis techniques is applied when a
critical path method calculation has been completed and resources availability is
critical?
What is the cost performance index?
The project budget is set at $150,000. The project duration is planned to be one
year.At the completion of Week 16 of the project, the following information is
collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What
is the cost performance index?
Which technique is utilized in the Control Schedule process?
Which technique is utilized in the Control Schedule process?