what is the schedule variance value?
Amy is working on a project which is forty percent complete though it was scheduled to be fifty
percent complete as of today. Management has asked Amy to report on the schedule variance for
her project. If Amy’s project has a BAC of $750,000 and she has spent $485,000 to date, what is
the schedule variance value?
Which of these does constructability take into account during analysis?
Samuel works as a project manager in Bluewell Inc. He is performing constructability analysis in
one of the initial planning phases. Which of these does constructability take into account during
analysis? Each correct answer represents a complete solution. Choose three.
What value do you report?
You are the project manager of a project that has a budget of $675,000 and you have completed
40 percent of the project work. Your project is supposed to be 60 percent complete but you are
actually only 40 percent complete. Due to some errors, however, you have actually spent
$335,000 of the budget. Management wants to know what the project’s cost performance index
(CPI) is. What value do you report?
How much capital should the project set aside for the risk contingency reserve?
You are the project manager of the GHE Project. You have identified the following risks with the
characteristics as shown in the following figure: How much capital should the project set aside for
the risk contingency reserve?
What must be true of these project activities for crashing to be acceptable?
Mary is the project manager for her company. She’s working with the project team to compress the
project schedule as the project must be completed by December 30. For some of the project
activities, she and the project team have agreed to crash the project work. What must be true of
these project activities for crashing to be acceptable?
What is the review of the late work commonly called?
Gary is the project manager for his organization. At each weekly status meeting with his project
team, Gary collects information on the work that has been completed and reviews the work that is
remaining in the project. Alice, one of Gary’s project team members, consistently reports that she’s
late on her project work. After the meeting, Gary and Alice discuss why the work is late as it is
causing other delays in the project. What is the review of the late work commonly called?
What does it mean to crash the project?
You have a project to install 45,900 emergency exit signs throughout a university campus. You
have a crew of 45 project team members to install the signs and they are making good progress
on the installation but it looks like they’ll miss the promised end date. Your project requires all of
the signs to be installed one week before classes are scheduled to begin. You elect to crash the
project in an effort to shorten the installation duration activity. What does it mean to crash the
project?
What is the schedule variance for this project that Fred needs to report to the management?
Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty
percent complete. Fred has crashed the project, which has driven the project costs to date to
$1,525,140, but his project is five percent more complete than what was planned. What is the
schedule variance for this project that Fred needs to report to the management?
What is the process in which Tom is working?
Tom works as the project manager for BlueWell Inc. He is working with his project to ensure timely
and appropriate generation, retrieval, distribution, collection, storage, and ultimate disposition of
project information. What is the process in which Tom is working?
Which calendar will communicate to the project stakeholders, when the project work will take place within the
You are the project manager for your organization. Management has asked you to document the
holidays, weekends, and other corporate working hours, which will supersede the project timings
for your schedule. Which calendar will communicate to the project stakeholders, when the project
work will take place within the organization?