What is this project’s schedule variance?

You are the project manager of the GHY Project. This project is scheduled to last for one year and
has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are

supposed to be at your second milestone which accounts for half of the project completion. There
have been some errors in the project, which has caused you to spend $2,073,654. What is this
project’s schedule variance?

What is the cost variance for this project that Fred needs to report to management?

Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty
percent complete. Fred has crashed the project, which has driven the project costs to date to
$1,525,140, but his project is five percent more complete than what was planned. What is the cost
variance for this project that Fred needs to report to management?

What is this project’s schedule performance index?

You are the project manager of the GHY Project. This project is scheduled to last for one year and
has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are
supposed to be at your second milestone which accounts for half of the project completion. There
have been some errors in the project which has caused you to spend $2,073,654. What is this
project’s schedule performance index?