what impact will his two days of lateness have on the project end date?

Mary is the project manager of the H1QZ Project. This project is a subproject of the HQZ Project
and the project schedule is fixed and cannot vary. Stephen, a project team member, reports that
he’s having trouble completing his project assignment and will likely be at least two days late.
Examine the figure given below:

If Stephen’s assignment is Activity B, what impact will his two days of lateness have on the project
end date?

Which of the following estimating techniques will you use for the highest degree of accuracy?

You have been hired as a contract project manager for Tech Perfect Inc. The project has already
been started. Sufficient details of the project have already been structured. You are working with
your team for cost estimation of the project. Which of the following estimating techniques will you
use for the highest degree of accuracy?

In this project, who is the lead person responsible for communication with all stakeholders?

Beth is the project manager of the KJH project. Sarah is Beth’s administrative assistant and Ben is
the project team leader. Beth’s project has eight virtual teams throughout the world that will be
working on the activities relevant to the deliverables in their locales. Thomas, the project sponsor,
has told Beth that he is to be kept abreast of all communication between her project and the
stakeholders. In this project, who is the lead person responsible for communication with all
stakeholders?