What is this project’s to-complete performance index based on the current BAC?
You are the project manager of the HQQ Project. Your project is running late by ten percent of
where you should be at this time. Management is concerned. Considering that the project has a
BAC of $567,899, you are thirty percent complete, and you have spent $179,450. What is this
project’s to-complete performance index based on the current BAC?
Which of the following is a tool and technique for the Schedule Development process?
Andy works as the project manager for Bluewell Inc. He is developing the schedule for the project.
There are eight tools and techniques that a project manager can use to develop the project
schedule. Which of the following is a tool and technique for the Schedule Development process?
What time will you record for this activity?
You are the project manager for your organization. You have recorded the following duration
estimates for an activity in your project: optimistic 20, most likely 45, pessimistic 90. What time will
you record for this activity?
How much float is available for Activity G to help offset the risk event?
You are the project manager of the NHQ Project. You have created the project network diagram
as shown in the figure:
You are concerned about a risk on Activity G that if it happens will delay the project by four days.
You would like to utilize float for Activity G. How much float is available for Activity G to help offset
the risk event?
This approach to project management planning is known as what?
Beth is the project manager for her organization. Her current project has many deliverables that
have been defined at a high level, but the details of the deliverables are still unknown. In her
project, Beth is planning in detail only the activities that are most imminent in the project work. This
approach to project management planning is known as what?
which one?
Gina is the project manager for her organization and she is working with her project team to define
the project activities. In this project, the stakeholders are sensitive to the project completion date,
so Gina is stressing to her project team members that while they need to provide and account for
all of the project activities, they should focus on one work package in the WBS at a time. In order
to start the decomposition of the project work packages into activities, Gina will need all of the
following except for which one?
What is the difference between total float and free float?
You have created the project network diagram for the ABC project. You are exploring total float
and free float for that project. Martin, a project team member, wants to know the difference
between total float and free float. What is the difference between total float and free float?
how much float is available for Activity H if Activity B is delayed by four days and Activity E is delayed by
How many more communication channels will Ben’s project have next week?
Ben is the project manager for his organization. His project has 26 stakeholders this week and will
have five additional stakeholders next week. How many more communication channels will Ben’s
project have next week?