How stakeholders are usually identified?
Adrian is the project manager for her project. This new project needs to identify all the
stakeholders that will be affected by the project’s outcome. How stakeholders are usually
identified?
What document should you update to address this situation?
You are the project manager of the NHQ Project. Management has told you that resource leveling
will be enforced on your project, but they still want you to complete the project by July 2. With the
current resources you have and the resource leveling imposed, you would not be able to finish by
the constraint. What document should you update to address this situation?
You need to report work performance information to management
You are creating a status report to show how your project is progressing. Management is
interested in several key activities and their status. You need to report work performance
information to management. All of the following are example of work performance information you
should include in your report except for which one?
Which of the following are the outputs to the Determine Budget process?
Which of the following are the outputs to the Determine Budget process? Each correct answer
represents a complete solution. Choose all that apply.
What forecasting method would your project use if your project customer requires an autoregressive moving aver
What forecasting method would your project use if your project customer requires an
autoregressive moving average for performance forecasting?
What two items can you compare in the critical chain method to determine if corrective action is appropriate?
You are the project manager of the GUH project. You are using the critical chain scheduling
method as your approach to project scheduling. What two items can you compare in the critical
chain method to determine if corrective action is appropriate?
The _______contains the schedule components and the rules for relating and using the components to represent t
CORRECT TEXT
Fill in the blank with an appropriate phrase. The _______contains the schedule components and
the rules for relating and using the components to represent the process for completing a project.
what is the estimate at completion for the NNQ Project?
Cathy is the project manager of the NNQ Project. She currently has completed 45 percent of the
project but was scheduled to have 65 percent of the project completed. This project has a budget
of $344,000 and was scheduled to last four months. Cathy has spent $198,998 to date on the
project. Based on this information, what is the estimate at completion for the NNQ Project?
What value should Maurice report?
Maurice is the project manager of the NHQ Project and his project team has just finished the
project activities. The quality control team reports that the project deliverables are perfect. The
only thing left to in the project is to verify scope. This process will be performed by the project
stakeholders. Maurice is required to submit a final project report and report on the project
performance. Maurice’s project had a budget of $234,000 but the project spent $245,000. In the
final report management wants to know the project’s cost performance index (CPI). What value
should Maurice report?
What are schedule activities on the critical path called?
You are the project manager of the GHQ Project. You are working with your project team to create
the project network diagram. You have created the PND and are identifying the critical path with
your team using your project management information system. All of the activities on the critical
path are showing in red in the software that you are using to evaluate the critical path. What are
schedule activities on the critical path called?