What document should you update to address this situation?

You are the project manager of the NHQ Project. Management has told you that resource leveling
will be enforced on your project, but they still want you to complete the project by July 2. With the
current resources you have and the resource leveling imposed, you would not be able to finish by
the constraint. What document should you update to address this situation?

what is the estimate at completion for the NNQ Project?

Cathy is the project manager of the NNQ Project. She currently has completed 45 percent of the
project but was scheduled to have 65 percent of the project completed. This project has a budget
of $344,000 and was scheduled to last four months. Cathy has spent $198,998 to date on the
project. Based on this information, what is the estimate at completion for the NNQ Project?

What value should Maurice report?

Maurice is the project manager of the NHQ Project and his project team has just finished the
project activities. The quality control team reports that the project deliverables are perfect. The
only thing left to in the project is to verify scope. This process will be performed by the project
stakeholders. Maurice is required to submit a final project report and report on the project
performance. Maurice’s project had a budget of $234,000 but the project spent $245,000. In the
final report management wants to know the project’s cost performance index (CPI). What value
should Maurice report?

What are schedule activities on the critical path called?

You are the project manager of the GHQ Project. You are working with your project team to create
the project network diagram. You have created the PND and are identifying the critical path with
your team using your project management information system. All of the activities on the critical
path are showing in red in the software that you are using to evaluate the critical path. What are
schedule activities on the critical path called?