What is the ETC for this project?

You are the project manager of the QAQ Project. The QAQ Project has a BAC of $2,786,121. You
are currently 20 percent complete with this project, though you should be 25 percent complete with
the project work. The project has consumed $595,000 of the project budget to date. Management
has asked you, based on the current project performance, what the project’s estimate to complete
will be considering the current project schedule variance. What is the ETC for this project?