What formula do you use to find the schedule performance index?
Management is concerned about your project. They want to know how the project is performing
specifically the schedule performance index. What formula do you use to find the schedule
performance index?
what will happen to the project duration?
You work as a project manager for BlueWell Inc. You want to increase the overall duration of the
project. If the management elects to use resource leveling, then what will happen to the project
duration?
What can you do to rectify this problem?
You work as a project manager for BlueWell Inc. Your project is falling behind though the project
team reports that the actual durations of their work is what they estimated. You investigate the
cause and determine that the project team is not starting their assignments early enough to finish
their work on time. While the duration of the assignments may be in synchronization with the
duration estimates, the completion time is causing the project schedule to slip from the baseline.
What can you do to rectify this problem?
What type of communication method are you using in this instance?
You are the project manager for your organization. You are meeting with your customers to
discuss the project performance. In this meeting, you will have eight project customers, the project
sponsor, and ten members of your project team. What type of communication method are you
using in this instance?
Which of the following components of the change control system includes the documentation, tracking systems
Which of the following components of the change control system includes the documentation,
tracking systems, and defined approval levels necessary for authorizing and controlling changes?
What is Holly’s schedule performance index for this project?
Holly is the project manager of the NDS project and she is 85 percent complete with her project
though she should be 95 percent complete. Her project has a BAC of $9,850,400 and she has
spent $8,011,221 to date. What is Holly’s schedule performance index for this project?
What value should you report to management based on your project’s performance?
You are the project manager of the JKM Project for your organization. Your project is supposed to
be 60 percent complete but you are only 45 percent complete. The project has an assigned
budget of $765,000 but you have already spent $365,000 to reach this point in the project due to
some errors and rework. Management is pressing you on when you’ll complete the project and
how much the project will likely cost based on the current performance. You need to tell
management what the project’s current cost performance index (CPI) is. What value should you
report to management based on your project’s performance?
What type of estimate have you created for management?
You are the project manager for the NHQ Project. Management has asked you to create a time
estimate for this project although you have only just received the project charter. They would like
some idea of how long the project will take based on the information in the project charter. While
you are uncomfortable giving any type of estimate at this point, you work with your assigned
project to create a quick time estimate. What type of estimate have you created for management?
how much float is available for Activity H if Activity B is delayed by four days and Activity D is delayed by
What is the formula for PERT?
You are the project manager for your organization. You are working with your project team to
create activity duration estimates using the PERT method. What is the formula for PERT?