PrepAway - Latest Free Exam Questions & Answers

Category: PMI-RMP

Exam PMI-RMP: PMI Risk Management Professional

What document is Frank and the NHH Project team creating in this scenario?

[tagged]
Frank is the project manager of the NHH Project. He is working with the project team to create a
plan to document the procedures to manage risks throughout the project. This document will
define how risks will be identified and quantified. It will also define how contingency plans will be
implemented by the project team. What document is Frank and the NHH Project team creating in
this scenario?

What is the cost performance index for this project to determine if the contingency response should happen?

Pete works as a project manager for BlueWell Inc. The Management has told him that he must
implement an agreed-upon contingency response if the cost performance index in his project is
less than 0.90. Consider that Pete’s project has a budget at completion of $275,000. His project is
65 percent complete and he has spent $175,000 to date. However, Pete is scheduled to be 78
percent complete. What is the cost performance index for this project to determine if the

contingency response should happen?

What should you tell Nancy?

You work as a project manager for BlueWell Inc. You are working with Nancy, the COO of your
company, on several risks within the project. Nancy understands that through qualitative analysis
you have identified 80 risks that have a low probability and low impact as the project is currently
planned. Nancy’s concern, however, is that the impact and probability of these risk events may
change as conditions within the project may change. She would like to know where will you
document and record these 80 risks that have low probability and low impact for future reference.
What should you tell Nancy?


Page 6 of 28« First...45678...20...Last »