What risk response is David proposing to management?

David is the project manager of the NKL Project for his organization. He has been asked to create
a proposal for a construction project for a client. David realizes that there are several requirements
within the SOW and RFP provided by the client that would eliminate his company from bidding on
the construction project. David proposed to management that his organization create a partnership
with a competitor so that together they could bid on the construction project and qualify for the
customer’s requirements. What risk response is David proposing to management?

What should Billy tell management if he’s following the best practices for risk management?

Billy is the project manager of the HAR Project and is in month six of the project. The project is
scheduled to last for 18 months. Management asks Billy how often the project team is participating
in risk reassessment in this project. What should Billy tell management if he’s following the best
practices for risk management?

Which one of the following is NOT a tool or technique that is appropriate for the quantitative risk analysis p

[tagged]
You work as a project manager for BlueWell Inc. You are about to complete the quantitative risk
analysis process for your project. You can use three available tools and techniques to complete
this process. Which one of the following is NOT a tool or technique that is appropriate for the
quantitative risk analysis process?

Which of the following risk processes is repeated after the plan risk responses to determine if the overall pr

[tagged]
You are the project manager of the NNN project for your company. You and the project team are
working together to plan the risk responses for the project. You feel that the team has successfully
completed the risk response planning and now you must initiate what risk process it is. Which of
the following risk processes is repeated after the plan risk responses to determine if the overall
project risk has been satisfactorily decreased?