What will be Neil’s reply to Tom?

Neil works as a project manager for SoftTech Inc. He is working with Tom, the COO of his
company, on several risks within the project. Tom understands that through qualitative analysis
Neil has identified many risks in the project. Tom’s concern, however, is that the priority list of
these risk events are sorted in “high-risk,” “moderate-risk,” and “low-risk” as conditions apply
within the project. Tom wants to know that is there any other objective on which Neil can make the
priority list for project risks. What will be Neil’s reply to Tom?

which risk response method is most appropriate?

Rex is the project manager of the BDF Project. This project will last for two years and has a
budget of $2,345,000. Management has instructed Rex that the project must not go over budget
as funds are very tight in the organization. During the project planning Rex and the project team
discover a positive risk event to save $75,000. Rex wants to make certain that this risk event
happens so which risk response method is most appropriate?

what other documentation will need to be updated as an output of risk response planning?

[tagged]
Joan is the project manager of the BTT project for her company. She has worked with her project
to create risk responses for both positive and negative risk events within the project. As a result of
this process Joan needs to update the project document updates. She has updated the
assumptions log as a result of the findings and risk responses, but what other documentation will
need to be updated as an output of risk response planning?