Which schedule development tool and technique produces a theoretical early start date late start date?
Which schedule development tool and technique produces a theoretical early start date late start date?
What is the minimum a project schedule must include?
What is the minimum a project schedule must include?
What cost control technique is used to compare actual project performance to planned or expected performance?
What cost control technique is used to compare actual project performance to planned or expected performance?
what is the Schedule Performance Index (SPI)?
Using the following data, what is the Schedule Performance Index (SPI)?
EV= $500
PV=$750
AC=$1000
BAC=$1200
Which enterprise enviromental factors are considered during cost estimating?
Which enterprise enviromental factors are considered during cost estimating?
Which process involves aggregating the estimated cost of the individual schedule activities or work packages?
Which process involves aggregating the estimated cost of the individual schedule activities or work packages?
What is the schedule performance index (SPI) using the following data?
What is the schedule performance index (SPI) using the following data?
BAC=$ 100,000
PV=$50,000
AC=$80,000
EV=$40,000
What is the actual status of this project?
The project manager calculated a schedule performance index 0.80 and a cost performance index 1.1 for the project. What is the actual status of this project?
Which of the following is a valid formula for calculating EAC?
EAC (Estimate and complete) is typically based on actual cost (AC) for work completed plus and ETC (Estimate to complete) the remaining work. Which of the following is a valid formula for calculating EAC?
Which of the following equations is used to calculate schedule variance?
Which of the following equations is used to calculate schedule variance?