What is the project’s cost performance index?

Mark works as a project manager of the NNH project. In this project, he has created a contingency
response that the cost performance index should be less than 0.91. The NHH project has a budget
at completion of $950,000 and is 43 percent complete – though the project should be 50 percent
complete. The project has spent $470,897 to reach the 43 percent complete milestone. What is
the project’s cost performance index?

What will be your reply?

You work as a project manager for BlueWell Inc. You are involved with the project team on the
different risk issues in your project. You are using the applications of IRGC model to facilitate the
understanding and managing the rising of the overall risks that have impacts on the economy and
society. One of your team member wants to know that what is the need to use the IRGC. What will
be your reply?

Which of the following is true regarding this scenario?

You are a program manager for an environmental program. The program involves installation of windmill across the country. During execution of the project, a stakeholder raises a change request to add an additional module with the existing installation. The program governance board has approved the change request. Which of the following is true regarding this scenario?