What is the project’s cost performance index?
Mark works as a project manager of the NNH project. In this project, he has created a contingency
response that the cost performance index should be less than 0.91. The NHH project has a budget
at completion of $950,000 and is 43 percent complete – though the project should be 50 percent
complete. The project has spent $470,897 to reach the 43 percent complete milestone. What is
the project’s cost performance index?
[tagged] Who makes Go/No-Go decisions during phase gate reviews?
[tagged]
Who makes Go/No-Go decisions during phase gate reviews?
What will be your reply?
You work as a project manager for BlueWell Inc. You are involved with the project team on the
different risk issues in your project. You are using the applications of IRGC model to facilitate the
understanding and managing the rising of the overall risks that have impacts on the economy and
society. One of your team member wants to know that what is the need to use the IRGC. What will
be your reply?
Which of the following tools/techniques keep program managers and executives informed of the program’s p
[tagged]
Which of the following tools/techniques keep program managers and executives informed of the program’s progress?
What is a pure risk?
Diana is the project manager of the QPS project for her company. In this project Diana and the
project team have identified a pure risk. Diana and the project team decided, along with the key
stakeholders, to remove the pure risk from the project by changing the project plan altogether.
What is a pure risk?
Which one of the following is the other one?
[tagged]
You are the program manager for your organization. Management has assigned you to a new program that has been chartered. Your team is in the process of the Manage Program Issues process. One of the two outputs of this process is change requests. Which one of the following is the other one?
What do you tell Bonny?
Management has asked you to perform a risk audit and report back on the results. Bonny, a
project team member asks you what a risk audit is. What do you tell Bonny?
Which of the following is true regarding this scenario?
You are a program manager for an environmental program. The program involves installation of windmill across the country. During execution of the project, a stakeholder raises a change request to add an additional module with the existing installation. The program governance board has approved the change request. Which of the following is true regarding this scenario?
how much will be left in the contingency reserve?
Which one of the following is not considered one of the three components of the Iron Triangle?
Which one of the following is not considered one of the three components of the Iron Triangle?