Where should you document the proposed responses and the current status of all identified risks?
[tagged]
You are the project manager of the HJK Project for your organization. You and the project team
have created risk responses for many of the risk events in the project. Where should you
document the proposed responses and the current status of all identified risks?
What is this limit of resource hours in a time period known as?
[tagged]
You are the program manager for your organization. As your program is being initiated there is some initial concern from the management about the utilization of resources in your program and the need for resources in their day-to-day roles in operations. Management has set a limit on your program that resources may only work 20 hours per week on the program. What is this limit of resource hours in a time period known as?
What is an Ishikawa diagram?
You are the project manager of the NGH project for your organization. You want to create a
causeand- effect diagram to help discover the root causes of the risks within the project. Harold,
the CIO, recommends that you create an Ishikawa diagram instead. What is an Ishikawa diagram?
What document should you specify in your program management plan for the conclusion of the program?
[tagged]
You are the program manager for your organization. You are planning a new program that will construct a new warehouse facility for your company. As you look forward to the conclusion of the program you need an official document that will signify the program has ended. What document should you specify in your program management plan for the conclusion of the program?
Which one of the following is NOT a tool or technique that is appropriate for the quantitative risk analysis p
[tagged]
You work as a project manager for BlueWell Inc. You are about to complete the quantitative risk
analysis process for your project. You can use three available tools and techniques to complete
this process. Which one of the following is NOT a tool or technique that is appropriate for the
quantitative risk analysis process?
which one of the following?
You are the program manager for your organization and are working with your team to create the program scope management plan. This plan defines several things in your program except for which one of the following?
What diagramming technique are you using as a part of the risk identification process?
[tagged]
You are the project manager of RTF project for your organization. You are working with your
project team and several key stakeholders to create a diagram that shows causal factors for an
effect to be solved. What diagramming technique are you using as a part of the risk identification
process?
What program selection method is management using in this instance?
[tagged]
Management is trying to determine which program to initiate. Each of the potential programs has the possibility of creating an income for each it is in existence. Management would like to consider the present value for each year a program creates a return on investment. What program selection method is management using in this instance?
Which of the following risk processes is repeated after the plan risk responses to determine if the overall pr
[tagged]
You are the project manager of the NNN project for your company. You and the project team are
working together to plan the risk responses for the project. You feel that the team has successfully
completed the risk response planning and now you must initiate what risk process it is. Which of
the following risk processes is repeated after the plan risk responses to determine if the overall
project risk has been satisfactorily decreased?
How many more communication channels will you have next week in your program?
You are the program manager for your program and are creating a communications management plan. Management wants you to address the type of communications based on the number of communication channels you’ll have within the program. Currently there are 345 stakeholders in your program but next week you’ll have 387 stakeholders. How many more communication channels will you have next week in your program?