What type of action have you provided in this scenario?

You are the program manager of the BHG Program. One of the projects in your program will be using new materials that are somewhat untested. You are worried that there may be delays and waste because the project team is unaware of how to accurately use these materials. You elect to send the people that will be using the new materials through training on how to complete their project work. You also allow them to purchase some of the materials to experiment on their use
before the actual project work is to be done. You want to ensure that mistakes don’t enter the project. What type of action have you provided in this scenario?

Which of the following risk response planning techniques will you use to shift the impact of a threat to a thi

[tagged]
You work as the project manager for Bluewell Inc. You are working on NGQQ Projectyou’re your
company. You have completed the risk analysis processes for the risk events. You and the project
team have created risk responses for most of the identified project risks. Which of the following
risk response planning techniques will you use to shift the impact of a threat to a third party,
together with the responses?

What is the Cost Performance Index for this project to determine if the contingency response should happen?

You are the project manager of the NHQ project for your company. Management has told you that
you must implement an agreed upon contingency response if the Cost Performance Index in your
project is less than 0.90. Consider that your project has a budget at completion of $250,000 and is
60 percent complete. You are scheduled to be however, 75 percent complete, and you have spent
$165,000 to date. What is the Cost Performance Index for this project to determine if the
contingency response should happen?