PrepAway - Latest Free Exam Questions & Answers

Author: seenagape

Which of the following inputs will be needed for the quantitative risk analysis process in her project?

[tagged]
Della works as a project manager for SoftTech Inc. She is working with the project stakeholders to
begin the quantitative risk analysis process. Which of the following inputs will be needed for the
quantitative risk analysis process in her project? Each correct answer represents a complete
solution. Choose all that apply.

Which one of the following is a likely reason why the project should be terminated?

Mary Anne is the program manager for her organization. In her program there are six projects. One of the projects in her program has been performing well. It is on schedule and has no cost or schedule variances. Mary Anne has decided, however, that her program needs to be terminated.
Which one of the following is a likely reason why the project should be terminated?

What things will you need as inputs for the quantitative risk analysis of the project in this scenario?

You are the project manager of the GGH Project in your company. Your company is structured as
a functional organization and you report to the functional manager that you are ready to move onto
the quantitative risk analysis process. What things will you need as inputs for the quantitative risk
analysis of the project in this scenario?

Which of the following is NOT an example of a cause for a project risk?

You are the project manager of the HQQ Project for your company. You are working with your
project stakeholders to discuss the risks in the project that can adversely affect the project
objectives. You are discussing the possibilities of causes for an identified risk event in your project.
Your stakeholder is confused on the difference between causes and risk events. Which of the
following is NOT an example of a cause for a project risk?

What type of risk response have you implemented in this situation?

You are the program manager of the GHY Program. Your program team has identified a risk dealing with the materials you will be using in the program. It is possible that if the materials are not installed properly they will cause serious damage in future phases of the program. Your team has recommended additional training and a consultant to help the team members install the material accurately to reduce the likelihood of the risk event. You agree and the team executes the risk response.
What type of risk response have you implemented in this situation?


Page 467 of 512« First...102030...465466467468469...480490500...Last »