What type of a risk response has Melody used in this scenario?
Melody is the project manager for her organization. She has created a risk response to conduct
more tests on the software her project is creating. The identified risk that prompted this response
was that the software is mission-critical and must be flawless before it can be put into product.
What type of a risk response has Melody used in this scenario?
Which of the following processes involves choosing the alternative strategies, executing a contingency or fall
[tagged]
Which of the following processes involves choosing the alternative strategies, executing a
contingency or fallback plan, taking corrective action, and modifying the project management
plan?
which one?
All of the following are resources that need to be monitored and controlled except for which one?
which risk response method is most appropriate?
Rex is the project manager of the BDF Project. This project will last for two years and has a
budget of $2,345,000. Management has instructed Rex that the project must not go over budget
as funds are very tight in the organization. During the project planning Rex and the project team
discover a positive risk event to save $75,000. Rex wants to make certain that this risk event
happens so which risk response method is most appropriate?
which one?
All of the following are resources that you will need to monitor and control in a program environment except for which one?
What schedule analysis simulation tool allows you, the project manager, to review possible combinations of eve
What schedule analysis simulation tool allows you, the project manager, to review possible combinations of events such as optimistic, most likely and pessimistic outcomes for your project?
What is the best policy for risks with low probability and low impact in the project management?
You are the project manager of the NJJ project. Your enterprise environmental factors require that
you establish certain risk management rules regarding low risks within your project. What is the
best policy for risks with low probability and low impact in the project management?
What group will need to review your program plan to approve the plan before you may proceed in the work?
[tagged]
You are the program manager for your organization. Your program will create a new condominium in your community. There are several concerns about the condos including the timing, the local economy, the environment, and the proposed schedule. You and your team are creating the program management plan to address these concerns along with identifying the constituent projects that will build the structures and deliverables. What group will need to review your program plan to approve the plan before you may proceed in the work?
what type of risk response?
Gary has identified a project risk that could injure project team members. He does not want to
accept any risk where someone could become injured on this project so he hires a professional
vendor to complete this portion of the project work. This workaround to the risk event is known as
what type of risk response?
What cost estimating approach uses the work breakdown structure to create a cost estimate?
What cost estimating approach uses the work breakdown structure to create a cost estimate?