Which of the following techniques are you using for risk identification?

You are the project manager for the TTR project. You are in the process of gathering information
for risk identification. You ask experts to participate in the process through their emails for
maintaining anonymity. You collect the responses, summarize them, and are then re-circulated to
the experts for further comment. Which of the following techniques are you using for risk
identification?

What type of a chart should you create for management?

[tagged]
You are the program manager for your organization. Management has asked you to create a method to track the program stakeholders’ concerns, threats, and demands for communication.
They would like you to map out each stakeholder or stakeholder group and identify trends within the chart to help your program communicate better. What type of a chart should you create for management?

What risk response has been used here?

Ben is the project manager of the CMH Project for his organization. He has identified a risk that
has a low probability of happening, but the impact of the risk event could save the project and the
organization with a significant amount of capital. Ben assigns Laura to the risk event and instructs
her to research the time, cost, and method to improve the probability of the positive risk event. Ben
then communicates the risk event and response to management. What risk response has been
used here?

Which one of the following is NOT an accomplishment of the qualitative risk analysis process?

You are the project manager of the GHQ project for your company. You are working with your
project team to prepare for the qualitative risk analysis process. Mary, a project team member,
does not understand why you need to complete qualitative risks analysis. You explain to Mary that
qualitative risks analysis helps you determine which risks needs additional analysis. There are
also some other benefits that qualitative risks analysis can do for the project. Which one of the
following is NOT an accomplishment of the qualitative risk analysis process?

The temperature of 430 is called what?

[tagged]
Your project uses a piece of equipment that if the temperature of the machine goes above 450
degree Fahrenheit the machine will overheat and have to be shut down for 48 hours. Should this
machine overheat even once it will delay the project’s end date. You work with your project to
create a response that should the temperature of the machine reach 430, the machine will be
paused for at least an hour to cool it down. The temperature of 430 is called what?

What name describes this type of end-of-phase review management is completing on your project?

[tagged]
You are the project manager for your organization. Your project team has finished the second phase of a seven-phase project. At the end of each phase, management must review the work your project team has completed and determine if the project should be allowed to continue. What name describes this type of end-of-phase review management is completing on your project?