Which of the following are included in the risk register?
You are the project manager for TTP project. You are in the Identify Risks process. You have to
create the risk register. Which of the following are included in the risk register? Each correct
answer represents a complete solution. Choose two.
what has been submitted in an attempt to find consensus?
[tagged]
You are the program manager for your organization and are working on gathering the requirements for a new solution and mission statement. There are several instances in the stakeholder pool where the stakeholders and their manager are being queried on possible requirements. You worry that the subordinates may have requirements, ideas, and suggestions to offer but they may be not submitting their thoughts because they do not want to contradict their managers. You believe you need a method to gather all requirements without the stakeholders having any fear of retribution. Which one of the following allows you to anonymously gather iterations requirements and still allow for all stakeholders to review what has been submitted in an attempt to find consensus?
what two inputs will she need?
Kelly is the project manager of the NNQ Project for her company. This project will last for one year
and has a budget of $350,000. Kelly is working with her project team and subject matter experts to
begin the risk response planning process. When the project manager begins the plan risk
response process, what two inputs will she need?
What is the minimum future value this organization should expect to receive from this program if it is initiat
An organization is considering a new program. The program has a cost of $1,950,000 and will last for three years. What is the minimum future value this organization should expect to receive from this program if it is initiated and the rate of return is six percent?
what risk response?
Your project is an agricultural-based project that deals with plant irrigation systems. You have
discovered a byproduct in your project that your organization could use to make a profit. If your
organization seizes this opportunity it would be an example of what risk response?
Which of the following inputs of the identify risks process is useful in identifying risks associated to the t
[tagged]
John works as a project manager for BlueWell Inc. He is determining which risks can affect the
project. Which of the following inputs of the identify risks process is useful in identifying risks
associated to the time allowances for the activities or projects as a whole, with a width of the range
indicating the degrees of risk?
what should you do with the issues?
You are the program manager for your organization and you’re dealing with several issues about the materials used in the program. Right now, the issues have been assigned to issue owners for resolution in ten days. In the interim, what should you do with the issues?
which one?
You work as a project manager for TechSoft Inc. You, the project team, and the key project
stakeholders have completed a round of quantitative risk analysis. You now need to update the
risk register with your findings so that you can communicate the risk results to the project
stakeholders – including management. You will need to update all of the following information
except for which one?
what component represents the disagreement of these two project managers and their refusal to speak with each
Two project managers in your program, Marcy and Mary, are not agreeing with the scheduling of project resources and they have asked for your help to determine the resolution. They are refusing to speak with each other and each is telling you that the other person is scheduling project resources for the project that are already scheduled to complete the work. In the communication model, what component represents the disagreement of these two project managers and their refusal to speak with each other about a resolution?
Which of the following types of risk response are you following?
You are the project manager for a construction project. The project involves casting of a column in
a very narrow space. Because of lack of space, casting it is highly dangerous. High technical skill
will be required for casting that column. You decide to hire a local expert team for casting that
column. Which of the following types of risk response are you following?