what is the risk exposure of the event that must be considered for the cost of the risk response?

You are the project manager of the KJH Project and are working with your project team to plan the
risk responses. Consider that your project has a budget of $500,000 and is expected to last six

months. Within the KJH Project you have identified a risk event that has a probability of .70 and
has a cost impact of $350,000. When it comes to creating a risk response for this event what is the
risk exposure of the event that must be considered for the cost of the risk response?

Which communication method is considered to be the best approach for this scenario?

[tagged]
Harriet is the program manager of a large program that has a high profile and visibility in her organization. Some of the stakeholders are negative and Harriet needs to work with these stakeholders to address their fears, perceived threats, and concerns about the program. Which communication method is considered to be the best approach for this scenario?

What is the estimate at completion?

You are the project manager of the NHJ project for your company. This project has a budget at
completion of $1,650,000 and you are 60 percent complete. According to the project plan,
however, the project should be 65 percent complete. In this project you have spent $995,000 to
reach this point of completion. There is a risk that this project may be late so you have taken some
measures to recover the project schedule. Management would like to know, based on current
performance, what the estimate at completion for this project will be. What is the estimate at
completion?