What is the present value of a program that will be worth $3,567,000 if it lasts for six years and the rate of
What is the present value of a program that will be worth $3,567,000 if it lasts for six years and the rate of return is five percent?
what is the risk exposure of the event that must be considered for the cost of the risk response?
You are the project manager of the KJH Project and are working with your project team to plan the
risk responses. Consider that your project has a budget of $500,000 and is expected to last six
months. Within the KJH Project you have identified a risk event that has a probability of .70 and
has a cost impact of $350,000. When it comes to creating a risk response for this event what is the
risk exposure of the event that must be considered for the cost of the risk response?
What must you do with the rejected change requests?
You are the program manager for the SRQ Program. You have rejected several change requests for the program scope. What must you do with the rejected change requests?
What risk identification technique allows participants to identify the project risks and to remain anonymous?
[tagged]
What risk identification technique allows participants to identify the project risks and to remain
anonymous?
Where are negative risks recorded?
[tagged]
Where are negative risks recorded?
which of the following processes is John working on?
[tagged]
John works as a project manager for ABD project. He and his team, are working on the following
activities:
Relative ranking or priority list of project risks
Watchlists of low priority risk
Trends in Qualitative Risk Analysis results
On which of the following processes is John working on?
what is the present value of the program if the interest rate is six percent?
You are the program manager for your organization. Management would like to consider the present value for your program. If your program is predicted to be worth $450,000 in two years what is the present value of the program if the interest rate is six percent?
Which one of the following is NOT an output of the process?
[tagged]
There are five outputs of the risk monitoring and controlling process. Which one of the following is
NOT an output of the process?
Which communication method is considered to be the best approach for this scenario?
[tagged]
Harriet is the program manager of a large program that has a high profile and visibility in her organization. Some of the stakeholders are negative and Harriet needs to work with these stakeholders to address their fears, perceived threats, and concerns about the program. Which communication method is considered to be the best approach for this scenario?
What is the estimate at completion?
You are the project manager of the NHJ project for your company. This project has a budget at
completion of $1,650,000 and you are 60 percent complete. According to the project plan,
however, the project should be 65 percent complete. In this project you have spent $995,000 to
reach this point of completion. There is a risk that this project may be late so you have taken some
measures to recover the project schedule. Management would like to know, based on current
performance, what the estimate at completion for this project will be. What is the estimate at
completion?