What else should Fred do to account for the twenty-four hours of cure time?

Fred is the project manager of a hotel restoration project. The hotel has 456 rooms. All rooms
need to be primed and painted. Before each room can be painted, the primer must cure for twenty-four hours. Fred has arranged these tasks with a finish to start relationship between the priming
and the painting. What else should Fred do to account for the twenty-four hours of cure time?

Which of the following are the necessary inputs?

You work as a project manager for Honeywell Inc. You have been distributing performance
information, including status reports, progress measurement, and forecasts to various
stakeholders. A trainee of this company wants to know what are the inputs for generating
performance reports. Which of the following are the necessary inputs? Each correct answer
represents a part of the solution. Choose two.

What part of your project has the largest variance?

You are the project manager of the GHY project. Your project has a BAC of $675,000 and is forty
percent complete though you were supposed to be forty-five percent complete. Due to some
errors early in the project, you had to spend $278,000 of your project’s budget to reach this point.
Management is asking for a variance report. What part of your project has the largest variance?