What does this figure depict?
You work as a Project Manager for Media Perfect Inc. Several projects are running under your
supervision. Rick, team leader of a project, provides you performance indexes of his project. The
schedule variance (SV) of his project is 25. What does this figure depict?
which of the following processes?
Rolling wave planning is used as tool and technique in which of the following processes?
Why is this information needed?
You are the project manager for the NQQ Project for your organization. You and the project team
are creating the activity list for the NQQ Project. You have instructed the project team members
that they should include an activity identifier and a scope of work description for each activity in the
activity list. Why is this information needed?
What is the critical path duration for the given schedule network?
What law of economics would prevent Harry from exponentially adding labor to the project work in an effort to
Harry is the project manager of a large network installation project. This project requires Harry to
add network cable to each office and cubicle of a 14-story office building. Harry will receive a
bonus for good time and cost performance in this project. What law of economics would prevent
Harry from exponentially adding labor to the project work in an effort to complete the work in a
very small amount of time?
What is the total float on path BEG?
What is the critical path of this project?
What is the earned Value (EV)?
If the schedule Variance (SV) = $55, and the Planned Value (PV) = $11, What is the earned Value (EV)?
What is the rate of risk factor in such a situation?
You work as a stakeholder for ABC Inc. You are on an important feature of a project that appears
too difficult to execute. Issues like acceptable type of bugs and number of bugs for user
acceptance seem to have affected the project. What is the rate of risk factor in such a situation?
What is the status of the project if the cost Performance index is 1.25 and the schedule Performance Index is
What is the status of the project if the cost Performance index is 1.25 and the schedule Performance Index is 0.75?