Which of the following is the best response for Mary’s query?

You are the project manager for GGY Project. You are working with your project team to record
the actual durations for the activities they have completed in the project schedule. Mary, one of
your project team members, wants to know why you need to know how long it actually took the
project team to complete their assignments as long as the project work is completed. Which of the
following is the best response for Mary’s query?

What is the SPI for this project?

You are the project manager of the NHQ Project. This project has a Budget at Completion of
$750,000 and is expected to take 18 months to complete. The project is supposed to be 75
percent complete, but due to some errors the project is only 60 percent complete. At this time the
project has spent $465,500. Management has asked you to review the project work and report the
project’s SPI. What is the SPI for this project?