Which one of the following can you present to the management as a part of the control schedule tools and techn

You are the project manager for your project. Your project is scheduled to last for one year and
you are currently forty percent complete with the project. Based on your current performance
measurements you have an SPI of .95 and a cost variance of -$24,000. You need to report this
information to the management, but you will also need a solution to present with the variance
information. Which one of the following can you present to the management as a part of the
control schedule tools and techniques for variances?