Which of the following documents will define the project justification?
Your organization wants to start a new project. The study shows that the new project will save
organization approximately $200,000 per year. Now it is required to move forward with the project.
Which of the following documents will define the project justification?
Which type of analysis is used as a general management technique within the Plan Procurements Process?
Which type of analysis is used as a general management technique within the Plan Procurements Process?
Which relationship type between activities are the most common?
You are the project manager of the NHQ Project. You are coaching Alice, a new project manager,
on the relationships in a project network diagram. Which relationship type between activities are
the most common?
Complete this sentence: _________________________ is the process of collecting and distributing performance in
Complete this sentence:
_________________________ is the process of collecting and distributing performance
information including status reports, progress measurements, and forecasts.
what type of contract?
A purchase order for a specific item to be delivered by specified date for a specified price is the simplest form of what type of contract?
what have you added in the project?
If you are the project manager of the BNQ Project and you add “waiting time” between two
activities, then what have you added in the project?
What is the tool and technique used to request seller responses?
What is the tool and technique used to request seller responses?
Which one of the following can you present to the management as a part of the control schedule tools and techn
You are the project manager for your project. Your project is scheduled to last for one year and
you are currently forty percent complete with the project. Based on your current performance
measurements you have an SPI of .95 and a cost variance of -$24,000. You need to report this
information to the management, but you will also need a solution to present with the variance
information. Which one of the following can you present to the management as a part of the
control schedule tools and techniques for variances?
which of the following?
A contract change control system defines which of the following?
What will likely happen to your project now?
You are the project manager for your organization. You have created the project schedule and
have presented it to the management for their approval. Management decides to enforce resource
leveling heuristics on your project schedule. What will likely happen to your project now?