Who is primrily responsible for the project being a risk?
ABC project is a risk for failling to achieve a major project objective due to unresolved stakeholder issues. Team member morale is low.
Who is primrily responsible for the project being a risk?
What term is assigned to this communication tool?
Ned is the project manager for his organization. Ned is using a standard tool to capture, store, and
distribute information to the stakeholders about the project costs, schedule, and performance.
What term is assigned to this communication tool?
which communication method works most effectively?
When communicating with large audiences, which communication method works most effectively?
which one?
All of the following statements about the critical path are false except for which one?
Which of the following tools/techniques will you use to demonstrate how a process behaves over time…?
You work as a project manager for BlueWell Inc. Which of the following tools/techniques will you
use to demonstrate how a process behaves over time, and when a process is subject to special
cause variation, resulting in an out-of-control condition?
What are assigned risk ratings based upon?
What are assigned risk ratings based upon?
What component of the change management system is responsible for evaluating, testing, and documenting changes
What component of the change management system is responsible for evaluating, testing, and
documenting changes created to the project scope?
Which of the following processes includes prioritizing risks for subsequent further analysis or action by asse
Which of the following processes includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?
Which one of the following is a valid response to the identified risk event?
Your project team has identified a project risk that must be responded to. The risk has been
recorded in the risk register and the project team has been discussing potential risk responses for
the risk event. The event is not likely to happen for several months but the probability of the event
is high. Which one of the following is a valid response to the identified risk event?
Which of the following documents allows the project manager to assess risks that may required near term action
Which of the following documents allows the project manager to assess risks that may required near term action?