Which knowledge area is concerned with the process required to ensure timely and appropriate generation…
Which knowledge area is concerned with the process required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?
What does this figure depict?
Della works as a Project Manager for BlueWell Inc. A number of projects are running under her
guidance. You, being a team leader of a project, provide Della the performance indexes of your
project. The schedule variance (SV) of your project is zero. What does this figure depict?
which process?
Forecasts, requested changes, recommended corrective actions, and organizational process asset updates are all outputs of which process?
What does Parkinson’s Law state about this scenario?
You are the project manager of the NQQ project. You are working with your project team to create
the activity duration estimates for the project. For each reported activity duration, your project team
offers you an addition of five percent extra time for risks, errors, or aggressive estimating. What
does Parkinson’s Law state about this scenario?
Which of the folowing is contained within the communications management plan
Which of the folowing is contained within the communications management plan
What is the best approach in this scenario?
You work as a project manager for BlueWell Inc. You are going through a project with your project
team. Some of your project team members are reporting that their activities are running late
because there are lag times between activities that do not need to be there. You examine the
schedule and see that the lag times have been incorporated into the project schedule for quality
control reviews. You also learn that the quality control reviews are not being completed as
planned. What is the best approach in this scenario?
which project management process?
Approved change requests, approved corrective actions, and updates to organizational process assets are all outputs of which project management process?
Which knowledge area employs the processes required to ensure timely and appropriate generation, collection
Which knowledge area employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retieval, and ultimate disposition of project information?
what is this project’s to-complete performance index?
You are the project manager of the GHY Project. This project is scheduled to last for one year and
has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are
upposed to be at your second milestone, which accounts for half of the project completion. There
have been some errors in the project, which has caused you to spend $2,073,654. Based on the
estimate at completion, what is this project’s to-complete performance index?
What is a technique used in the performance reporting process?
What is a technique used in the performance reporting process?