What is your cost variance for this project?

You are the project manager of the NHA Project. This project is expected to last one year with
quarterly milestones throughout the year. Your project is supposed to be at the third milestone
today, but you are likely to be only 60 percent complete. Your project has a BAC of $745,000 and
you have spent $440,000 of the budget-to-date. What is your cost variance for this project?