What does Anna want to create in this instance?

Anna is the project manager of the NHQ project. Her project has 1,500 stakeholders, some of
which are external to her organization. In this project, Anna wants to create a method to classify
the stakeholders based on their level of authority and their level of concern regarding the project
outcomes. This model will help Anna determine the communication demands and when
information should be distributed. What does Anna want to create in this instance?