What is the schedule performance index (SPI) using the following data?
What is the schedule performance index (SPI) using the following data?
BAC=$ 100,000
PV=$50,000
AC=$80,000
EV=$40,000
What type of communication should be generated based on this performance issue?
You work as the project manager for BlueWell Inc. You are recording the activity status for your
project team’s performance in the project. Based on the current performance your project is likely
to be three months late. What type of communication should be generated based on this
performance issue?
What is the actual status of this project?
The project manager calculated a schedule performance index 0.80 and a cost performance index 1.1 for the project. What is the actual status of this project?
What is the planned value for this project?
You are the project manager of the NHQ project. Your project has a budget of $1,258,456 and is
scheduled to last for three years. Your project is currently forty percent complete though it should
be forty-five percent complete. In order to reach this point of the project, you have spent $525,000.
Management needs a performance report regarding the NHQ project. What is the planned value
for this project?
Which of the following is a valid formula for calculating EAC?
EAC (Estimate and complete) is typically based on actual cost (AC) for work completed plus and ETC (Estimate to complete) the remaining work. Which of the following is a valid formula for calculating EAC?
What is the formula used for PERT?
You are the project manager for the GRT Project in your organization. You have created your time
duration estimates based on historical information, but the estimates are not holding true in your
current project. Unfortunately, many activities are late. You have decided to create a PERT
estimate with your project team for each of their activities. What is the formula used for PERT?
Which of the following equations is used to calculate schedule variance?
Which of the following equations is used to calculate schedule variance?
What scheduling method is Terri using in this example?
Terri is the project manager for her organization and she is working with her project team to
develop the project schedule. She has identified the float in her project although some of the
activities where float exists may be susceptible to risk in the project execution. She is also
concerned that the critical path may change during the project if the risk events come into
execution. What scheduling method is Terri using in this example?
Which tool and technique uses a statical relationship between historical data and other variables to calculate
Which tool and technique uses a statical relationship between historical data and other variables to calculate estimates?