Which of the following documents would not be an input for the control schedule process?

You are the project manager for your organization. You are managing a project to create new
software for your clients. During the project execution, there have been some unforeseen delays
that will require your attention. You will need four inputs to the control schedule process. Which of
the following documents would not be an input for the control schedule process?

you need to help sequence the project work?

You are the project manager of the NHQ project. You are working with your project team to create
the project schedule and the project network diagram. In order to start the sequencing of the
project activities, you will need a document to identify the result of project phases, key project
deliverables, and significant, timeless events in the project. Which of the following documents will
you need to help sequence the project work?