What type of planning are you using in this project?

You are the project manager of a research project. Because much of the project work will be
based on what is discovered in each stage of the project work, you are directing the project time to
focus on creating time estimates for the most imminent research work and broad estimates for the
project work that is coming later in the project. What type of planning are you using in this project?