What is the schedule variance for this project that Fred needs to report to the management?

Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty
percent complete. Fred has crashed the project, which has driven the project costs to date to
$1,525,140, but his project is five percent more complete than what was planned. What is the
schedule variance for this project that Fred needs to report to the management?

Which calendar will communicate to the project stakeholders, when the project work will take place within the

You are the project manager for your organization. Management has asked you to document the
holidays, weekends, and other corporate working hours, which will supersede the project timings
for your schedule. Which calendar will communicate to the project stakeholders, when the project
work will take place within the organization?