Holly is the project manager for her organization. In her project, she has worked with the project
team to define when the project team will be utilized in the project, the duration of the project
activities, and the sequence in which the project work must be completed. During several phases
of her project, the project team will need to work more than fifty hours per week. The project team
members have agreed this is necessary and they’re willing to do the work to complete the project.
Management, however, has not approved Holly’s schedule based on the overtime the scheduling
will require. They have set a limit on the project schedule of 45 hours per week. What is this limit
technically called? Each correct answer represents a complete solution. Choose all that apply.
When do stakeholders have the greatest influence?
When do stakeholders have the greatest influence?
What value do you report?
You are the project manager of a project that has a budget of $675,000 and you have completed
40 percent of the project work. Your project is supposed to be 60 percent complete but you are
actually only 40 percent complete. Due to some errors, however, you have actually spent
$335,000 of the budget. Management wants to know what the project’s cost performance index
(CPI) is. What value do you report?
Which of the following provides a comprehensive and consistent method of controlling the project and ensuring
Which of the following provides a comprehensive and consistent method of controlling the project and ensuring its success?
what is the schedule variance value?
Amy is working on a project which is forty percent complete though it was scheduled to be fifty
percent complete as of today. Management has asked Amy to report on the schedule variance for
her project. If Amy’s project has a BAC of $750,000 and she has spent $485,000 to date, what is
the schedule variance value?
Which type of project phasing will allow for the most flexibility in the delivering the full product when prod
Company A is delivering a product in three parts. The contract allows for the parts to be delivered either one after other or at the same time.
Which type of project phasing will allow for the most flexibility in the delivering the full product when product requirements are subject to rapid change?
Which of these does constructability take into account during analysis?
Samuel works as a project manager in Bluewell Inc. He is performing constructability analysis in
one of the initial planning phases. Which of these does constructability take into account during
analysis? Each correct answer represents a complete solution. Choose three.
which type of organization does a project manager have a moderate-to-high resource availability?
In which type of organization does a project manager have a moderate-to-high resource availability?
Which Stakeholder is responsible for managing related projects in a coordinated way?
Which Stakeholder is responsible for managing related projects in a coordinated way?
which of the following organizational structures does the project manager have full authority on a project?
In which of the following organizational structures does the project manager have full authority on a project?