What is the estimate at completion for this project that Harry will need to report to management?
Harry works as a project manager for the NHQ project. His project has a budget of $2,208,456 and
is scheduled to last for three years. His project is currently forty percent complete though it should
be forty-five percent complete. In order to reach this point of the project, he has spent $725,000.
Management needs a performance report regarding the NHQ project. Management is concerned
that this project will be over budget upon completion. What is the estimate at completion for this
project that Harry will need to report to management?
Which of the following correctly explains the term (Progressive elaboration) ?
Which of the following correctly explains the term (Progressive elaboration) ?
A project Management office (PMO) manages a number of aspects, including what?
A project Management office (PMO) manages a number of aspects, including what?
What will be the cost performance index (CPI) of the project at the current point of time?
You work as a Project Manager for Dreams Unlimited Inc. You are looking for performance
efficiencies of a project. The related key values are provided in the table below:
MeasurementsValues
BCWP (or EV)325
BCWS (or PV) 300
ACWP (or AC)410
What will be the cost performance index (CPI) of the project at the current point of time?
What is a function of the project managemet office (PMO) ?
What is a function of the project managemet office (PMO) ?
What action can help Tom to manage the errors in the project and to ensure that the errors would not occur aga
Tom is the project manager of the HQQ Project. His project has a schedule variance of -$34,500
due to some errors early in the project. Management would like to know how Tom will respond to
these variances. What action can help Tom to manage the errors in the project and to ensure that
the errors would not occur again?
which of the following at the project level?
A project manager is responsible for managing which of the following at the project level?
What type of an estimate are you creating in this scenario?
You work as a project manager for BlueWell Inc. Your project requires the project team to paint
1,500 hotel rooms. Your project team reports that it will take them approximately 4 hours to paint
each hotel room. You reason, then, that it will take 6,000 hours to paint all of the hotel rooms.
What type of an estimate are you creating in this scenario?
Resource B s roles is that of a
Company A is launching a new communications satellite system. Resource B was assigned combined projects of design, construction, integration, and launch of the satellite.
Resource B s roles is that of a
Which organizational theory explains the factors that promote performance of people in any organization?
Which organizational theory explains the factors that promote performance of people in any
organization?