what project document must be updated to reflect this change to the approach?
Holly is the project manager of her project. She has chosen to crash the project due to time
constraints that have been imposed on her project. When Holly crashes the project what project
document must be updated to reflect this change to the approach?
The schedule baseline is a component of what?
You work as a project manager for BlueWell Inc. There have been changes to the project scope in
your project. These changes will cause the project schedule to change as well, so you will need to
update the schedule and the schedule baseline. The schedule baseline is a component of what?
Which of the following schedule network analysis techniques is applied when a critical path method calculation
Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
Which path is considered the critical path?
Examine the figure given below: Which path is considered the critical path?
Which of the following outputs from the schedule control process aids in the communication of SV, SPI or any p
Which of the following outputs from the schedule control process aids in the communication of SV, SPI or any performance status to stakeholders?
What other tool Winnie can use to help and generate an updated project schedule?
Winnie is the project manager for her company. She has been recording the actual durations of
the project work to determine the actual progress of her project. Winnie needs to generate an
updated project schedule based on project performance. She is using the supporting schedule
data, manual scheduling methods, and her project management software to perform schedule
network analysis. What other tool Winnie can use to help and generate an updated project
schedule?
Which technique is utilized in the Schedule Control Process?
Which technique is utilized in the Schedule Control Process?
What is the estimate at completion for this project that you will need to report to management?
You are the project manager of the NHQ project. Your project has a budget of $1,258,456 and is
scheduled to last for three years. Your project is currently forty percent complete though it should
be forty-five percent complete. In order to reach this point of the project, you have spent $525,000.
Management needs a performance report regarding the NHQ project. Management is concerned
that this project will be over budget upon completion. What is the estimate at completion for this
project that you will need to report to management?
which of the following processes?
Cost Baseline is an output of which of the following processes?
Which of the following are the inputs to the Develop Project Charter process?
Which of the following are the inputs to the Develop Project Charter process? Each correct answer
represents a complete solution. Choose all that apply.