What other tool Winnie can use to help and generate an updated project schedule?

Winnie is the project manager for her company. She has been recording the actual durations of
the project work to determine the actual progress of her project. Winnie needs to generate an
updated project schedule based on project performance. She is using the supporting schedule
data, manual scheduling methods, and her project management software to perform schedule
network analysis. What other tool Winnie can use to help and generate an updated project
schedule?

What is the estimate at completion for this project that you will need to report to management?

You are the project manager of the NHQ project. Your project has a budget of $1,258,456 and is
scheduled to last for three years. Your project is currently forty percent complete though it should
be forty-five percent complete. In order to reach this point of the project, you have spent $525,000.
Management needs a performance report regarding the NHQ project. Management is concerned
that this project will be over budget upon completion. What is the estimate at completion for this
project that you will need to report to management?