what project execution technique?
You are the project manager of the NHT Project. This project has 12,345 office doors to install
throughout a campus. Each of the doors costs the project $456 and requires special hardware to
electronically lock and open the doors. You’ve gathered the project team before they begin the
installation for a hands-on training. As a group you and the project team install 50 doors following
a checklist of instructions so that every door will be installed exactly the same throughout the
campus and with minimal waste. This is an example of what project execution technique?
Which of the following are inputs to activity Definition?
Which of the following are inputs to activity Definition?
what is the schedule variance value?
Your project is forty percent complete though it was scheduled to be fifty percent complete as of
today. Management has asked that you report on the schedule variance for your project. If your
project has a BAC of $650,000 and you’ve spent $385,000 to date, what is the schedule variance
value?
what Project Time Management Process?
Activity resource requirement and resource breakdown structure are outputs from what Project Time Management Process?
What is Parkinson’s Law?
Jim is the project manager for his project. He and his project team are creating their duration
estimates for the work packages in the WBS. For each activity, Jim is adding a few hours to the
duration estimate in case something goes wrong during the completion of the work activity. Sarah,
the project sponsor, does not approve of this and warns Jim of Parkinson’s Law. What is
Parkinson’s Law?
what Project Time Management process?
Project scope statement and resource calendars are inputs to what Project Time Management process?
Which type of scheduling would be required in such a scenario?
You work as a project manager for ABC Inc. You are currently overseeing a project on a high-rise
building site. Your prime concern is to ensure that cranes are used effectively for moving
materials. You also have to ensure that delivery trucks do not have to wait in a queue and that
workers on the upper floors are able to get their deliveries on time. Which type of scheduling
would be required in such a scenario?
Which of the following tools or techniques is used for Estimate Activity Duration?
Which of the following tools or techniques is used for Estimate Activity Duration?
how many communication channels exist within this project?
John works as a project manager for BlueWell Inc. He is working on a high-profile project with 80
stakeholders and he needs to express to his project team and to the management the importance
of communication in the project. He would like to show the number of stakeholder communication
channels in the project. Based on this information how many communication channels exist within
this project?
Which activity duration estimating technique incorporates additional timing for contingency purposes?
Which activity duration estimating technique incorporates additional timing for contingency purposes?