how should you schedule the lead time for the cabinet delivery?

You are the project manager for your organization. You need the oak cabinets for your project
delivered by December 1 in order to install the floors around the oak cabinets by December 15.
Your company’s procurement office generally takes 45 days to complete procurement orders.
Based on this information, how should you schedule the lead time for the cabinet delivery?

What is the to-complete performance index for this project?

Your project has a BAC of $750,000 and is 75 percent complete. According to your plan, however,
your project should actually be 80 percent complete. You have spent $575,000 of your project
budget to reach this point and you are worried about the project not being able to complete based
on your current project budget. What is the to-complete performance index for this project?